Finishing Touches

We are so close to finishing now we can almost taste it! To God be the glory!  Thank you for your continued prayers!!!

Left to be done:

Paving

Planting shrubs

Painting parking lines

Sign installation

Handicap sign installation

Finishing touchup

Caulking and painting crown molding

Cleanup

Furnishing

Moving from Oak Harbour Village storefront location

July Progress

Thank you so much for all your prayers!  God has been so good–we are very close to being done!  Please continue to pray for safety and wisdom.  Thank you so much!

Still to be done (condensed version):

Fire Relief Water Cistern installed

Kitchen appliances installed

Trim work/Finish Carpentry

Finish Plumbing

Furnishing

Decorating

Paint touch up

Parking Lot/Finish Grading/Painting of Parking Lot

Landscaping

Fence/Swingset installed

Handicap Parking signs ordered and installed

Church sign ordered and installed

Sound System installed

Flyers/Mailings/Newspaper Ads/Personal Invitations